I decided it is time to put the fuse’s side skins on. I just don’t see any benefits in keeping them off any longer Clecoed skins and doublers Started riveting right skin Spent 4 hours  

Started work on Section 29A – Forward upper fuselage. Completed the first 4 steps and a half of the step 5 Lots of drilling and rivet squeezing.   Spent 4 hours

Attached brakes hydrophilic tubes to master cylinders and setup the rest of the plumbing. The task turned out to be a bit harder than I expected It is done anyway and the section 27 is completed now. Spent 5 hours